With construction originally planned over a 16-month period, delays in permitting and approvals pushed Borea to work through an unseasonably wet spring, overcome additional delays in turbine delivery, and meet an accelerated COD date for the customer.
Borea completed 33 km of soil-stabilized roads, poured 20,000 m3 of concrete, installed the Siemens direct drive turbines for their first time, and completed all reclaim activities to the landowners’ satisfaction during this tight timeline.